RFC 434 UNKNOWN INFRASTRUCTURE · MAINTENANCE

IMP/TIP memory retrofit schedule

Schedule for upgrading the network's memory-bearing machines during early 1973.

On rfc-editor.org ↗
PUBLISHED
January 1973
AUTHORS
A.M. McKenzie
STREAM
Legacy
OBSOLETED BY
RFC 447 — IMP/TIP memory retrofit schedule
IMP MEMORY AFTER RETROFIT
16K words
TIP MEMORY AFTER RETROFIT
28K or 32K words
RETROFIT PERIOD
January to April 1973
DOI
10.17487/RFC0434

RFC text

Original text · RFC Editor View on rfc-editor.org ↗
Network Working Group                              Alexander A. McKenzie
RFC 434                                            BBN-NET
NIC 13658                                          January 4, 1973


                    IMP/TIP MEMORY RETROFIT SCHEDULE

   During the first several months of 1973 we will be retrofitting each
   IMP and TIP with additional core memory.  At the end of the retrofit
   program, the memory sizes of the various machines will be as follows:

      IMP (516 or 316) - 16K words

      TIP - 28K words

      TIP with magnetic Tape Option - 32K words

   In addition, the expansion of the TIP core memory will necessitate
   enlarging the TIP to two cabinets.

   Listed below is the preliminary schedule for these retrofits.  We
   have arranged this schedule to coincide with the usual monthly
   Preventive Maintenance at each site so as to minimize user
   inconvenience, but the work required will frequently require the
   machines to be down longer than normal.  I will issue additional
   RFC's updating this schedule as necessary.

   Any site which anticipate difficulty with the expansion of TIP size,
   and thus the floor space requirement, should contact Hawley Rising
   (BBN) at
      (617)491-1850 ext. 473
   All dates given below are in the form (month/day)

   Xerox (1/3)
   SAAC (1/4)
   MIT (1/8)
   MITRE (1/9)
   Harvard (1/15)
   RAND (1/16)
   ARPA (1/16)
   NBS (1/17)
   AMES TIP (1/24)
   Lincoln (1/24)
   Utah (2/1)
   UCSB (2/6)
   Belvoir (2/8)
   NOAA (2/12)
   USC (2/13)
   Stanford (2/14)
   ETAC (2/15)
   Aberdeen (2/22)
   ISI (2/22)
   Case (2/26)
   SRI (3/7)
   Rome (3/14)
   FNWC (3/15)
   UCLA (3/19)
   CCA (3/20)
   AMES IMP (3/21)
   GWC (3/22)
   Carnegie (4/4)
   SDC (4/17)
   Illinois (4/18)


         [ This RFC was put into machine readable form for entry ]
         [ into the online RFC archives by Alex McKenzie with    ]
         [ support from GTE, formerly BBN Corp.             9/99 ]

AI ELI5

On this page
PROBLEMThe packet-switching machines in ARPANET (IMPs and TIPs) needed more memory to handle growing network traffic, but the upgrades required shutting each machine down.
MECHANISMBBN published a month-by-month schedule for retrofitting memory in each machine during early 1973, timed to coincide with each site's existing monthly preventive maintenance window.
INFRASTRUCTURE UPGRADEThe upgrades doubled memory in IMPs to 16K words and increased TIP memory from 16K to 28K or 32K words, but some TIPs had to expand to two cabinets.

§1Introduction

During the first several months of 1973, BBN retrofitted every IMP (Interface Message Processor) and TIP (Terminal Interface Processor)—the network's packet-switching machines—with additional core memory. IMPs would receive 16K-word cores, and TIPs would be upgraded to 28K or 32K words depending on whether they had magnetic tape options.

All the network's message routers were getting more memory to work faster.

§2Impact on the Network

The expansion of TIP core memory required some machines to grow to two cabinets, which meant sites needed to prepare additional floor space. The upgrades were scheduled during each site's normal monthly preventive maintenance window, but the work sometimes required longer downtime than a routine maintenance visit.

Some computer boxes got bigger, so the computer rooms had to rearrange their space.

§3Retrofit Schedule

The schedule ran from January through April 1973, with sites distributed across all four months. Xerox and SAAC went in January, MIT and others in February and March, with the final machines such as Illinois scheduled for April. Sites that anticipated floor space problems were asked to contact BBN's Hawley Rising in advance.

Each network location got an appointment for the upgrade, staggered so BBN could do them one at a time.